R1/beta4 Timeline
A lot of these actions will be coordinated by the release coordinator and a sysadmin.
- 31 October - 4 November: one week - last minute scramble.
- Policy Don't commit anything risky.
- Promotion team begin investigating physical CD's or USB sticks?
- Policy "Soft" strings freeze begins.
- Testing Testing starts ramping up.
- 1 November: branch!
- Sysadmin Branch
r1beta4
- Policy
r1beta4
branch bug fix only! - Sysadmin Add
r1beta4
to concourse - Sysadmin Concourse and Buildmaster should be generating
r1beta4
TCs when forced. - Sysadmin No haikuports branch, not enough infrastructure. We didn't branch Haikuports for prior releases
- Sysadmin Generate an image and name it "Test Candidate 0"
- Sysadmin Upgrade HaikuPorter Buildmaster to beta branch TC0 image
- ICU upgrades?, build new webkit?
- Opened logo contest for installer logo
- Sysadmin Branch
- 2 November - 16 November: two weeks of xtreme testing
- Sysadmin Generate additional "Test Candidate" images as needed for testing.
- Development Work on fixing issues?
- Testing All hands on deck testing of test images.
- Unless any unfixable showstoppers are found, don't halt the release.
- Do general polishing of release notes, website, etc. during this time.
- 16 November - 23 November: one week to "get the goods"
- One final strings synchronization
- Sysadmin Generate an image and name it "Release Candidate 0".
- Begin work on draft https://www.haiku-os.org/get-haiku/release page (Draft = true)
- MOAR TESTING!
- 23 November - 30 November: one week of ham-fisting final images
- Promotion team physical CD's or USB sticks?
- Sysadmin Rename your latest release candidate to
r1beta4
, move from haiku-r1beta3/XXX to haiku-release/r1beta3/ - Sysadmin Double and triple check sha256 sums
- Sysadmin Generate a torrent, begin seeding and get a few other people to seed.
- Sysadmin Give a few hours for release to make it to the mirrors.
- Sysadmin Force a sync to Wasabi
- DO not advertise final release images on Wasabi.. too much bandwidth.
- Sysadmin Sync up working mirrors and release-r1b4
- Sysadmin Force a sync to Wasabi
- Sysadmin Push final images to IPFS repos and alert folks pinning to repin
- Sysadmin Pin R1 / Beta 4 release folder CID on Pinata
- Sysadmin Update website
- Release when ready; some window to account for unexpected delays.