== R1/beta5 Timeline == A lot of these actions will be coordinated by the release coordinator and a sysadmin. * **22 July - 29 July**: one week - last minute scramble. * **Policy** Don't commit anything risky. * **Promotion team** begin investigating physical CD's or USB sticks? * **Policy** "Soft" strings freeze begins. * **Testing** Testing starts ramping up. * **29 July**: branch! * **Sysadmin** Branch {{{r1beta5}}} * **Policy** {{{r1beta5}}} branch bug fix only! * **Sysadmin** Add {{{r1beta5}}} to concourse * **Sysadmin** Concourse and Buildmaster should be generating {{{r1beta5}}} TCs when forced. * **Sysadmin** No haikuports branch, not enough infrastructure. We didn't branch Haikuports for prior releases * **Sysadmin** Generate an image and name it "Test Candidate 0" * **Sysadmin** Upgrade HaikuPorter Buildmaster to beta branch TC0 image * ICU upgrades? * openssl3 update? And required updates of curl, webkit, etc to match. * **30 July - 13 August**: two weeks of **xtreme** testing * **Sysadmin** Generate additional "Test Candidate" images as needed for testing. * **Development** Work on fixing issues? * **Testing** ''All hands on deck'' testing of test images. * Unless any unfixable showstoppers are found, don't halt the release. * Do general polishing of release notes, website, etc. during this time. * **13 August - 20 August**: one week to "get the goods" * One final strings synchronization * **Sysadmin** Generate an image and name it "Release Candidate 0". * Begin work on draft https://www.haiku-os.org/get-haiku/release page (Draft = true) * MOAR TESTING! * **20 August - 27 August**: one week of ham-fisting final images * **Promotion team** physical CD's or USB sticks? * **Sysadmin** Rename your latest release candidate to {{{r1beta5}}}, move from haiku-r1beta5/XXX to haiku-release/r1beta5/ * **Sysadmin** Double and triple check sha256 sums * **Sysadmin** Generate a torrent, begin seeding and get a few other people to seed. * **Sysadmin** Give a few hours for release to make it to the mirrors. * **Sysadmin** Force a sync to Wasabi * DO not advertise final release images on Wasabi.. too much bandwidth. * **Sysadmin** Sync up working mirrors and release-r1b5 * **Sysadmin** Update website * Release when ready; some window to account for unexpected delays.