| 1 | = Release Coordination = |
| 2 | |
| 3 | This page acts as a status whiteboard for this release of Haiku. It should contain a list of tasks that need to be completed. |
| 4 | == Task List == |
| 5 | |
| 6 | This is a list of tasks that need to be done in preparation for the alpha 1 release. Do you see a task that still needs someone to take care of it? Drop a line on the [http://www.haiku-os.org/community/ml Haiku-Development] mailing list. |
| 7 | |
| 8 | === Build Tasks === |
| 9 | ||'''task'''||'''due'''||'''assignee'''||'''notes'''|| |
| 10 | ||Assign buildmeister|| - || - || |
| 11 | ||Determine distribution structure|| - || - || |
| 12 | ||Determine optional packages to be included|| - || - || - || |
| 13 | ||Set up a test framework/formal list of requirements|| - || - || |
| 14 | |
| 15 | === Release Preparation === |
| 16 | ||'''task'''||'''due'''||'''assignee'''||'''notes'''|| |
| 17 | ||Find mirrors|| - || - || |
| 18 | ||Write release notes|| - ||everyone||See wiki page ReleaseNotes || |
| 19 | ||Write press release|| - || - || |
| 20 | ||Determine press plan|| - || - || |
| 21 | |
| 22 | === Website === |
| 23 | ||'''task'''||'''due'''||'''assignee'''||'''notes'''|| |
| 24 | |
| 25 | |
| 26 | === Release === |
| 27 | ||'''task'''||'''due'''||'''assignee'''||'''notes'''|| |
| 28 | ||Branch the source tree|| - || - || |
| 29 | ||Backport important bug fixes|| - || - || |
| 30 | ||Tag the final build|| - || - || |
| 31 | ||Make source available|| - || - || |
| 32 | ||Test final build|| - || - || |
| 33 | ||Distribute final build to mirrors|| - || - || |
| 34 | |
| 35 | Note, dates are in dd-mm-yyyy format. |
| 36 | |
| 37 | == Release Schedule == |
| 38 | |
| 39 | * Branching trunk : - |
| 40 | * Final testing before tagging branch : - |
| 41 | * Tagging branch : - |
| 42 | |
| 43 | The testing of the build is expected to take a few days (pending any unforeseen problems). The website team will also require a few days to upgrade the website in order to support the release. The expected release date is around '''DATE'''. |
| 44 | |
| 45 | |
| 46 | == Proposals == |
| 47 | |
| 48 | There was a discussion, then followed a vote, and now we have a list of proposals for this release. Below is the final list of accepted proposals. |
| 49 | |
| 50 | |
| 51 | == Status Updates == |
| 52 | |
| 53 | The status updates give an overview of the progress that is made towards this release. |
| 54 | |
| 55 | |
| 56 | == Blocker issues == |
| 57 | |
| 58 | These need to be fixed in order to release the alpha. |
| 59 | |
| 60 | '''EDIT TicketQuery:'''[[TicketQuery(priority=blocker&status=new|assigned|reopened&milestone=R1/alpha1)]] |
| 61 | |
| 62 | '''EDIT TicketQuery:''' Total of [[TicketQuery(status=new|assigned|reopened&priority=blocker&milestone=R1/alpha1,count)]] open ticket(s). |
| 63 | |
| 64 | == Critical issues == |
| 65 | |
| 66 | If all the ''blocker'' items are resolved, these should be evaluated whether or not they block the alpha release. |
| 67 | |
| 68 | '''EDIT TicketQuery:'''[[TicketQuery(priority=critical&status=new|assigned|reopened&milestone=R1/alpha1)]] |
| 69 | |
| 70 | Total of '''EDIT TicketQuery:'''[[TicketQuery(status=new|assigned|reopened&priority=critical&milestone=R1/alpha1,count)]] open ticket(s). |
| 71 | |
| 72 | == High priority issues == |
| 73 | |
| 74 | This is a list of items with things that would be very much appreciated for this release, but they will not delay the release. |
| 75 | |
| 76 | '''EDIT TicketQuery:'''[[TicketQuery(priority=high&status=new|assigned|reopened&milestone=R1/alpha1)]] |
| 77 | |
| 78 | Total of '''EDIT TicketQuery:'''[[TicketQuery(status=new|assigned|reopened&priority=high&milestone=R1/alpha1,count)]] open ticket(s). |
| 79 | |