     1= Release Coordination  =
     2
     3This page acts as a status whiteboard for this release of Haiku. It should contain a list of tasks that need to be completed.
     4== Task List ==
     5
     6This is a list of tasks that need to be done in preparation for the alpha 1 release. Do you see a task that still needs someone to take care of it? Drop a line on the [http://www.haiku-os.org/community/ml Haiku-Development] mailing list.
     7
     8=== Build Tasks ===
     9||'''task'''||'''due'''||'''assignee'''||'''notes'''||
     10||Assign buildmeister|| - || - ||
     11||Determine distribution structure|| - || - ||
     12||Determine optional packages to be included|| - || - || - ||
     13||Set up a test framework/formal list of requirements|| - || - ||
     14
     15=== Release Preparation ===
     16||'''task'''||'''due'''||'''assignee'''||'''notes'''||
     17||Find mirrors|| - || - ||
     18||Write release notes|| - ||everyone||See wiki page ReleaseNotes ||
     19||Write press release|| - || - ||
     20||Determine press plan|| - || - ||
     21
     22=== Website ===
     23||'''task'''||'''due'''||'''assignee'''||'''notes'''||
     24
     25
     26=== Release ===
     27||'''task'''||'''due'''||'''assignee'''||'''notes'''||
     28||Branch the source tree|| - || - ||
     29||Backport important bug fixes|| - || - ||
     30||Tag the final build|| - || - ||
     31||Make source available|| - || - ||
     32||Test final build|| - || - ||
     33||Distribute final build to mirrors|| - || - ||
     34
     35Note, dates are in dd-mm-yyyy format.
     36
     37== Release Schedule ==
     38
     39 * Branching trunk : -
     40 * Final testing before tagging branch : -
     41 * Tagging branch : -
     42
     43The testing of the build is expected to take a few days (pending any unforeseen problems). The website team will also require a few days to upgrade the website in order to support the release. The expected release date is around '''DATE'''.
     44
     45
     46== Proposals ==
     47
     48There was a discussion, then followed a vote, and now we have a list of proposals for this release. Below is the final list of accepted proposals.
     49
     50
     51== Status Updates ==
     52
     53The status updates give an overview of the progress that is made towards this release.
     54
     55
     56== Blocker issues ==
     57
     58These need to be fixed in order to release the alpha.
     59
     60'''EDIT TicketQuery:'''[[TicketQuery(priority=blocker&status=new|assigned|reopened&milestone=R1/alpha1)]]
     61
     62'''EDIT TicketQuery:''' Total of [[TicketQuery(status=new|assigned|reopened&priority=blocker&milestone=R1/alpha1,count)]] open ticket(s).
     63
     64== Critical issues ==
     65
     66If all the ''blocker'' items are resolved, these should be evaluated whether or not they block the alpha release.
     67
     68'''EDIT TicketQuery:'''[[TicketQuery(priority=critical&status=new|assigned|reopened&milestone=R1/alpha1)]]
     69
     70Total of '''EDIT TicketQuery:'''[[TicketQuery(status=new|assigned|reopened&priority=critical&milestone=R1/alpha1,count)]] open ticket(s).
     71
     72== High priority issues ==
     73
     74This is a list of items with things that would be very much appreciated for this release, but they will not delay the release.
     75
     76'''EDIT TicketQuery:'''[[TicketQuery(priority=high&status=new|assigned|reopened&milestone=R1/alpha1)]]
     77
     78Total of '''EDIT TicketQuery:'''[[TicketQuery(status=new|assigned|reopened&priority=high&milestone=R1/alpha1,count)]] open ticket(s).
     79