R1 Beta 1 Timelines
The following timelines have been proposed for Beta 1
- two weeks - last minute scramble. Don't commit anything risky.
- Branch R1B1
- Tag R1B1rc1
- 1 month - *Bug fixes only*
- All hands on deck testing of release candidates.
- Documentation work.
- Weekly release candidates. Release Coordinator can adjust as needed.
- Release is frozen
- Point of no return, RC can no longer stop the release at this point.
- 1 week Final testing and documentation of known bugs.
- Final public release.