R1/beta1 Timeline
- 18 Aug - 25 Aug: one week - last minute scramble.
- Don't commit anything risky.
- "Soft" strings freeze begins.
- Testing starts ramping up.
- 25 Aug: branch
r1beta1
!- Buildbot and Buildmaster should be generating beta1 RCs
- Don't forget about HaikuPorts!
- 25 Aug - 7 Sep:
- All hands on deck testing of release candidates.
- Unless any unfixable showstoppers are found, don't halt the release.
- Do general polishing of release notes, website, etc. during this time.
- 7 Sep - 10 Sep
- Finalization of the "golden masters" (should just be images picked from the buildbot)
- One final strings synchronization
- 10 Sep - 18 Sep
- Release when ready; some window to account for unexpected delays.