Changes between Version 8 and Version 9 of R1/Beta3/Timeline


Ignore:
Timestamp:
Jun 5, 2021, 11:40:06 PM (3 years ago)
Author:
kallisti5
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • R1/Beta3/Timeline

    v8 v9  
    33> DRAFT: This is a draft and will likely change!!!!
    44
     5A lot of these actions will be coordinated by the release coordinator and a sysadmin.
     6
    57  * **13 June - 20 June**: one week - last minute scramble.
    6     * Promotion team, begin investigating physical CD's or USB sticks?
    78    * Don't commit anything risky.
     9    * **Promotion team** begin investigating physical CD's or USB sticks?
    810    * "Soft" strings freeze begins.
    911    * Testing starts ramping up.
     
    1719    * ICU upgrades, build new webkit?
    1820  * **26 June - 10 July**: two weeks of **xtreme** testing
    19     * Generate additional test candidate images as needed for testing.
     21    * Generate additional "Test Candidate" images as needed for testing.
    2022    * ''All hands on deck'' testing of test images.
    2123    * Unless any unfixable showstoppers are found, don't halt the release.
     
    2729    * MOAR TESTING!
    2830  * **17 July - 24 July**: one week of ham-fisting final images
    29     * Promotion team, physical CD's or USB sticks?
     31    * **Promotion team** physical CD's or USB sticks?
    3032    * Rename your latest release candidate to {{{r1beta3}}}, move from haiku-r1beta3/XXX to haiku-release/r1beta3/
    3133    * Double and triple check sha256 sums